AI data centers and Louisiana's power grid
AI data centers use enormous amounts of electricity, and in Louisiana new gas power plants are being built to supply them. This page tracks what is proposed, who decides, and what it could mean for power bills in New Orleans and Metairie. It is checked by hand against news reports and public filings.
Who sets your power rates
- Orleans Parish (New Orleans): Entergy New Orleans, regulated by the New Orleans City Council. A separate utility with its own rates. The City Council, not the state, approves its power plants and rates.
- Jefferson Parish (Metairie, Kenner, the West Bank): Entergy Louisiana, regulated by the Louisiana Public Service Commission (LPSC). The same utility building the power plants for Meta's data center, so the LPSC's decisions on those plants can affect its customers' rates.
Projects
Meta Hyperion data center
Richland Parish (northeast Louisiana). 3 gas plants, about 2,262 MW, approved in 2025; 7 more, about 5,278 MW, proposed in 2026.
Phase 1 plants under construction: two in Richland Parish (late 2028) and one at Entergy's Waterford site in St. Charles Parish (by the end of 2029). The 7-plant expansion (4 in Richland, 3 in Pointe Coupee Parish), with batteries and new transmission lines, is in LPSC docket U-37882, with a vote expected in December 2026.
Sources: The Lens (UCS analysis), Aug 2026 · Fox 8, Apr 2026 · WWNO, Nov 2026
Hut 8 River Bend campus
West Feliciana Parish (near St. Francisville). 330 MW from Entergy Louisiana for the first lease, with room for up to 1,000 MW more.
Under construction. A 15-year, 245 MW lease to Fluidstack, backed by Google; later reporting describes the capacity as built for Anthropic. First data hall due in the second quarter of 2027.
Sources: Hut 8 press release, Dec 2025 · DCD
New Orleans East proposal
Near I-10 and Read Boulevard, New Orleans. Not disclosed.
Withdrawn. The developer pulled its zoning permit hours after the City Council's January 28, 2026 vote to pause data centers.
Sources: WWNO, Jan 2026
Decisions so far
- 2025-08-20, LPSC: Approves Entergy Louisiana's three gas plants, about 2,262 MW, to power Meta's Richland Parish data center. Source
- 2025-12-17, LPSC: Adopts the "Lightning" directive, 4-1: power plants for very large customers can skip competitive bidding, with a decision due within about eight months. Source
- 2026-01-28, New Orleans City Council: Votes 6-0 to pause data centers (and crypto mining) citywide for a year while the City Planning Commission writes zoning rules. Source
- 2026-04-15, LPSC: Votes 4-1 to fast-track Entergy Louisiana's application for seven more gas plants for Meta. Source
- 2026-06-01, St. Charles Parish Council: Adopts its first data center zoning: industrial districts only, a 300-foot buffer from homes and schools, and a noise cap. In April it had rejected an eight-month moratorium, 5-3. Source
- 2026-07-22, New Orleans planning staff: Recommend banning the largest data centers (over 100,000 sq ft and 20 MW) citywide and allowing smaller ones in some districts, subject to review by Entergy New Orleans and the Sewerage and Water Board. Source
- 2026-08-12, LPSC: Votes 3-1 to overturn a judge's order that Meta provide its job and power-demand figures in the expansion case. Source
- 2026-10-13, New Orleans City Planning Commission: Votes 5-2 against the staff recommendation and extends the suspension, asking for more information and community input. Source
- 2026-11-05, LPSC staff: Reach a settlement with Entergy Louisiana that Entergy says resolves all outstanding issues on the seven-plant expansion; the Commission is set to vote in December. Source
- 2026-11-09, Landowner groups: Sue the LPSC in state court, arguing the Lightning directive was adopted without proper public notice. Source
Next: December 16, 2026: the LPSC is scheduled to consider the seven-plant expansion for Meta at its Business and Executive Session (docket U-37882).
What it could mean for your bill
- Entergy Louisiana says: Meta's contract covers the full cost of serving it, and the agreement is projected to produce net savings for other customers over 20 years.
- Critics say: Consumer and environmental groups (the Alliance for Affordable Energy, the Union of Concerned Scientists, Earthjustice) argue that fuel and some transmission costs are spread to all customers, and that customers could be left paying for the plants if Meta leaves early.
Compiled by hand from news reports, company releases and public filings; last checked 2026-11-16.
For general information only, not financial, legal, tax or insurance advice, an appraisal or proof of ownership. Owner names and parcel records are shown as published in public records and aren't verified. NOLA Atlas is independent and not affiliated with the Assessors, the City, FEMA or any data provider. Sources and methods.